Kaiser Bottom Fish OnlineFree trialNew StuffHow It WorksContact UsTerms of UseHome
Specializing in Canadian Stocks
SearchAdvanced Search
Welcome Guest User   (more...)
Home / Research Tools
Research Tools
 Corporate Profile: Artemis Gold Inc
    Publisher: Kaiser Research Online
    Author: Copyright 2019 John A. Kaiser

 
Artemis Gold Inc (ARTG-V)
Trade DateVolumeHighLowCloseChgStatus
March 28, 2024111,600$8.21$7.90$8.12$0.02Trading
KRO Profile - Members OnlyCorporate Web Site Not AvailableTreeExchQuote
Issued
198,009,701
Price
$8.120
Working Capital
$36,925,661
Key People: Steven G. Dean (CEO), Gerrie Van der Westhuizen (CFO), Jeremy Langford (COO),
Diluted
236,403,085
Insiders
10.4%
As of
9/30/2023
Company supplied Corporate Overview - not available
The free corporate profile serves as a fast gateway for KRO members via the map cards to resources such as the KRO Profile which includes financial, insider and project details as well as news releases and KRO comments for which headline links are provided below. Links to the company's web site and project web pages are available within this free corporate profile if the company has a multi-user corporate membership (they are always available in full member only KRO Profile). A corporate membership provides the company with complete multiple user access to KRO resources and entitles the company to provide a corporate overview for the subject company's unrestricted corporate profile.

Active Project List
ProjectCountryState/ProvRegionNet
Interest
StageIPV $
MM
Target MetalsDeposit StyleTSC
(Project Name has a link to its location in the Members only KRO Profile)
BlackwaterCanadaBritish ColumbiaCentral BC100% WI7-Permitting & Feasibility $1,915GoldDisseminated / Vein
Company Project Gateway
Blackwater Project
Company Project Web Page - N/A Canada - British Columbia 100% WI7-Permitting & Feasibility GoldDisseminated / Vein
Company News Releases - Members Only
Mar 12, 2024Filing of 2023 Financial Results
Feb 26, 2024Granting of Stock Options and Share Units
Feb 21, 2024Results of Expansion Study for Blackwater Mine
Jan 30, 2024Q4 Update on Blackwater Mine Construction Progress
Dec 15, 2023First Draw Under Project Loan Facility
Nov 7, 2023Filing of Q3 2023 Financial Results
Oct 24, 2023Q3 Update on Blackwater Mine Construction Progress
Aug 15, 2023Q2 2023 Financial Results and Provides Construction Progress Update
Aug 10, 2023AGM Voting Results
Aug 3, 2023Returns to Full Construction at Blackwater
Jul 17, 2023Update on Impact of the Wildfires in Central B.C. on Blackwater Mine
Jul 10, 2023Takes Precautionary Measures due to Wildfires in Central B.C.
Jul 4, 2023Receipt of Fisheries Act Authorization
Jun 19, 2023Granting Of Stock Options
Jun 15, 2023Approval of Schedule 2 Amendment for Blackwater Mine
Jun 15, 2023Optimized Phase 1 Development of Blackwater Mine and US$40M Additional Funding; Updated Phase 1 Capex Now Fully Funded
Jun 9, 2023Receives Initial Deposit Under Silver Stream Agreement
May 25, 2023Filing of Q1 2023 Financial Results
May 17, 2023Update on Site Activities at Blackwater Mine
May 9, 2023Corporate Updates
May 4, 2023Initiates Gold Hedging Program for Blackwater
Apr 20, 2023Over 11,000 Hectares Secured for Caribou Habitat and Restoration in Central B.C.
Apr 13, 2023Orders Primary and Ancillary Operations Mining Fleet
Mar 29, 2023Filing of Q4 2022 Financial Results
Mar 20, 2023Update on Process Plant Construction for the Blackwater Mine
Mar 13, 2023Granting of Stock Options
Mar 9, 2023Obtains BC Mines Act Permit for Blackwater Mine
Mar 1, 2023Closes $385 million project loan financing and $40 million standby cost overrun facility
Feb 27, 2023BC Mines Act Permit Referred for Decision
Feb 21, 2023Orders construction fleet
Jan 3, 2023Permitting & site works progress update
Dec 8, 2022Senior Management Changes
Nov 8, 2022Filing of Q3 2022 Financial Results
Oct 14, 2022Prospectus Share Offering
Oct 14, 2022Closes $175 Million Equity Financing
Oct 5, 2022Up to $175 Million Equity Financing
Oct 5, 2022Voting Results of Annual General Meeting
Oct 5, 2022Voting results of annual general meeting
Sep 29, 2022Commencement of Blackwater plant site earthworks
Sep 19, 2022Commencement of site works at Blackwater
Sep 12, 2022Granting of Stock Options
Sep 8, 2022Prices Final EPC Contract for the Process Plant with Sedgman At $318 million
Aug 11, 2022Filing of Q2 2022 Financial Results
Aug 11, 2022Land Blessing Ceremony at Blackwater
Jul 28, 2022Executes Master Lease Agreement with Caterpillar Financial
Jun 9, 2022Secures Long Lead Time Equipment Orders For Crushing And Grinding Equipment At Blackwater
May 24, 2022Artemis Awards Mining Fleet Supply For Blackwater Project, Secures Credit approved Commitment Letter For Equipment Lease Facility And Establishes Pathway To Fleet Decarbonization
May 19, 2022Filing Of Q1 2022 Financial Results
May 2, 2022Awards Process Plant Epc To Sedgman For The Blackwater Gold Project
Mar 31, 2022Filing Of 2021 Year End Financial Results And Provides Update On Blackwater
Feb 24, 2022Executes Credit approved Commitment Letter For $385 Million Project Debt Financing To Develop Blackwater
Dec 30, 2021Update On Epc Contract On Blackwater Process Plant
Dec 13, 2021Artemis And Wheaton Complete Cad $176 Million (US $141 Million) Silver Stream Agreement New Gold Waives Rofr; Wheaton Precious Acquires Blackwater Gold Stream From New Gold
Dec 13, 2021Inclusion In The Gdxj
Nov 16, 2021Receives Silver Stream Offer from Wheaton Precious Metals for CAD $176 Million (US $141 Million) Providing Additional Funding for the Development of Blackwater
Oct 25, 2021Files NI 43 101 Technical Report for Blackwater Feasibility Study
Oct 8, 2021Granting of Stock Options
Sep 13, 2021Feasibility Study for Blackwater Project
Aug 23, 2021Makes Final Cash Payment to New Gold in Respect of its Acquisition of the Blackwater Project
Aug 18, 2021Awards GMP (Guaranteed Maximum Price) on Blackwater Electricity Transmission Line
Aug 11, 2021Voting Results of Annual General Meeting
Jul 15, 2021Province Approves Early Works Permit for Artemis Gold's Blackwater Project
Jun 30, 2021Nomination of Two Additional Directors to the Board in Connection with its Upcoming AGM
Jun 23, 2021Provides Final Results of Grade Control Drilling of High Grade Near Surface Mineralization
Jun 1, 2021Private Placement Non Brokered
May 27, 2021Signing of IBA with Nazko First Nation
May 25, 2021Closes Non Brokered Private Placement Component of $171 Million Equity Financing; Reports Cash Position of $204 Million
May 21, 2021Prospectus Share Offering, Correction
May 20, 2021Prospectus Share Offering
May 19, 2021Closes Bought Deal Component of $171 Million Equity Financing, Including Full Exercise of Over Allotment Option
May 10, 2021Up to $156 Million Equity Financing
May 4, 2021Provides Interim Results of Grade Control Drilling of High grade Near Surface Mineralization
May 3, 2021Appoints Elise Rees to Board of Directors
Apr 27, 2021Engages the Terron Group in Support of ESG Commitment
Apr 9, 2021Executes Credit Approved Term Sheet and Mandate for $360 Million Project Debt Financing to Develop Blackwater
Mar 29, 2021Awards GMP (Guaranteed Maximum Price) on Blackwater Process Plant
Mar 26, 2021Increase in Ownership of Common Shares of Velocity Minerals Ltd
Mar 26, 2021Receives Notice of Early Conversion of $5,094,000 Convertible Debenture from Artemis Gold
Mar 1, 2021Provides Update on Blackwater Site Activities
Feb 24, 2021Makes Submission for Schedule 2 Amendment Process as Part of the Final Permitting Process for Blackwater
Feb 9, 2021Submits Early Works Permit Applications for Blackwater Gold Project
Feb 8, 2021Appointment of Key Senior Personnel
Jan 27, 2021Appointment of VP Finance
Jan 6, 2021Appointment of COO
Dec 7, 2020Presents Initial 2020 Metallurgical Test Work Results Confirming Key PFS Assumptions for Blackwater DFS
Nov 11, 2020Presents Key Data on Near Surface High Grade Mineralization at Blackwater
Nov 5, 2020Results from Blackwater Economic Impact Study
Nov 2, 2020Company Tier Reclassification
Oct 30, 2020Graduation to Tier 1 Status on the TSX Venture Exchange
Sep 18, 2020Files NI 43 101 Technical Report
Sep 3, 2020Private Placement Non Brokered
Sep 2, 2020Completion of Non Brokered Private Placement of $1,362,500
Aug 27, 2020Non Brokered Private Placement Of $1,362,500 And Granting Of Stock Options
Aug 26, 2020Revised PFS for Blackwater Project
Aug 24, 2020Property Asset or Share Purchase Agreement
Aug 24, 2020Appointment of Key Personnel
Aug 24, 2020Artemis Announces Closing of the Acquisition of the Blackwater Project from New Gold
Aug 11, 2020Shareholder Approval for Private Placement of Subscription Receipts to Related Parties
Jul 8, 2020Beedie Investments Limited Early Warning Press Release Regarding Investment in Artemis Gold Inc.
Jul 7, 2020Closing of $175 Million Private Placement of Subscription Receipts
Jun 12, 2020Upsize to C$175 Million on the Previously Announced Private Placement of Subscription Receipts
Jun 12, 2020Up to C$155 Million Private Placement of Subscription Receipts
Jun 9, 2020To Acquire Blackwater Project From New Gold
Oct 24, 2019Grant of Stock Options

 
 

You can return to the Top of this page


Copyright © 2024 Kaiser Research Online, All Rights Reserved